From lobby toward inside.

hangchoi

Quote from: chin on 14 March 2010, 22:55:35
I can almost reach the drop ceiling.  :o
Why so low?

I don't understand neither.......Do they want to flush the ceiling for all room? Can they move the lowest installation up to increase the headroom?

Even the window, is it necessary to flush the ceiling to the window guard?? Can a bulkhead be used??
「吾心信其可行,則移山倒海之難,終有成功之日。吾心信其不可行,則反掌折枝之易,亦無收效之期也。」

chin

19-Mar-2010

Start laying floor tile in the lobby area.

chin

19-Mar-2010

They worker put small pegs between the tiles to maintain a small space between tiles, so the tiles can expand a bit.

chin

19-Mar-2010

This AC unit fans out 1:4.

The fire service work from nominated contractor. This pipe is yet to be cut.

chin

19-Mar-2010

This guy working on the details (抆灰?) on the conference room light fixture.

chin

19-Mar-2010

Wiring closest. Quite a job to tell which is which.

AC work. Seem they lay the completely sealed metal duct first, then cut open the duct at the appropriate location for the AC outlet. The piece of metal on the floor is the cut out duct from above.

chin

19-Mar-2010

Views from two opposite ends.

chin

19-Mar-2010

The large manager room. The AC ducting is not yet cut.

Outside the room the networking guys are wiring CAT5 cables, 24 cable at a time.

chin

19-Mar-2010

Details under a big beam. And north side of the office.