Post by: chin on 03 March 2010, 01:42:16
2月25號收樓

2月28號彈線差不多完成,電梯前地台起出。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:21:19
3月5日

電梯大堂兩旁景,風機已裝,假天花支架上好。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:25:00
3月5日

辦公室中央東西兩景。
會議室和經理室正在做牆身。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:29:21
3月5日

大會議室,還未掘地。
不是所有房間的牆都上到頂。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:29:59
3月5日

CEO的辦公室?
Title: Re: DYX
Post by: chin on 05 March 2010, 23:32:27
3月5日

牆身埋窗口位,沒有鑽孔,只是用膠紙。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:33:59
3月5日

如果牆身不是對正窗框的間牆方法。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:34:57
3月5日

牆身電位。
Title: Re: DYX
Post by: chin on 05 March 2010, 23:36:08
3月5日

各色裝修物料。
風喉一早做好彎位?
Title: Re: DYX
Post by: chin on 05 March 2010, 23:38:07
3月5日

Screeding有5cm?!?!
看來只有1cm。已經看到鋼根!
Title: Re: DYX
Post by: hangchoi on 06 March 2010, 10:34:19
It shows some progress of the work......

Yep, most of the air ducts are now pre-fabricated off-site, as the dimensions of the fan coil units are quite standard.

It seems that the screeding is quite thin and the reinforcement bar should not be exposed when you chase the screeding. Maybe the contactor can use the ceiling more for cable routing, or use 20mm dia. conduit only for cable containment on floor.

What is the fitting out period?? How long did they start the work?? Seems they still need 2 months to complete the work at least.....
Title: Re: DYX
Post by: chin on 06 March 2010, 11:22:22
Work started on 26 or so.
Title: Re: DYX
Post by: chin on 11 March 2010, 00:05:02
3月10日

入口接待處。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:06:45
3月10日

大會議室外,內。上好隔音棉。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:11:26
3月10日

冷氣風機,風槽差不多全部上好。冷水管只裝了半層,未接上風機。

下面的風機未上罩?
Title: Re: DYX
Post by: chin on 11 March 2010, 00:12:41
3月10日

辦公室中央東西兩景。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:13:44
3月10日

其中兩個小會議室。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:15:20
3月10日

大經理房。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:16:33
3月10日

裝修物料是?天花?
Title: Re: DYX
Post by: chin on 11 March 2010, 00:17:21
3月10日

西面還在放冷氣喉。
Title: Re: DYX
Post by: chin on 11 March 2010, 00:17:55
3月10日

北面景色。  :)
Title: Re: DYX
Post by: chin on 14 March 2010, 22:53:12
14 March 2010

Working on drop ceiling in the large conference room. The drop ceiling seems too low for my personal preference. The light fixture in the middle is even lower than the ceiling.

2nd pic the corner conference room.
Title: Re: DYX
Post by: chin on 14 March 2010, 22:54:34
From east look toward the west, then reverse. The 3rd pic is NE corner looking toward the lobby.
Title: Re: DYX
Post by: chin on 14 March 2010, 22:55:35
I can almost reach the drop ceiling.  :o
Why so low?
Title: Re: DYX
Post by: chin on 14 March 2010, 22:56:30
Window curtain guard?
Title: Re: DYX
Post by: chin on 14 March 2010, 22:57:37
The chilled water pipe insulation material, and the fan coil box.
Title: Re: DYX
Post by: chin on 14 March 2010, 22:59:03
Partly insulated pipes.
And the size of the pipe reduce the further the pipe reaches.
Title: Re: DYX
Post by: chin on 14 March 2010, 22:59:46
Why some fan coils has 3 "holes" and some has none?
Title: Re: DYX
Post by: chin on 14 March 2010, 23:01:07
"嘩佬" to stop chilled water from entering the fan coil?
Title: Re: DYX
Post by: chin on 14 March 2010, 23:01:36
Pantry
Title: Re: DYX
Post by: chin on 14 March 2010, 23:02:31
From lobby toward inside.
Title: Re: DYX
Post by: hangchoi on 14 March 2010, 23:10:07
I can almost reach the drop ceiling.  :o
Why so low?

I don't understand neither.......Do they want to flush the ceiling for all room? Can they move the lowest installation up to increase the headroom?

Even the window, is it necessary to flush the ceiling to the window guard?? Can a bulkhead be used??
Title: Re: DYX
Post by: chin on 21 March 2010, 02:10:55
19-Mar-2010

Start laying floor tile in the lobby area.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:13:00
19-Mar-2010

They worker put small pegs between the tiles to maintain a small space between tiles, so the tiles can expand a bit.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:16:46
19-Mar-2010

This AC unit fans out 1:4.

The fire service work from nominated contractor. This pipe is yet to be cut.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:19:08
19-Mar-2010

This guy working on the details (抆灰?) on the conference room light fixture.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:23:19
19-Mar-2010

Wiring closest. Quite a job to tell which is which.

AC work. Seem they lay the completely sealed metal duct first, then cut open the duct at the appropriate location for the AC outlet. The piece of metal on the floor is the cut out duct from above.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:25:31
19-Mar-2010

Views from two opposite ends.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:27:08
19-Mar-2010

The large manager room. The AC ducting is not yet cut.

Outside the room the networking guys are wiring CAT5 cables, 24 cable at a time.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:28:50
19-Mar-2010

Details under a big beam. And north side of the office.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:30:02
19-Mar-2010

The fresh air supply duct is connected to 4 AC units on the west side. This one fresh air intake supplies all fresh air to the whole floor.
Title: Re: DYX
Post by: chin on 21 March 2010, 02:35:33
19-Mar-2010

Details of insulation on AC piping. Can see the chilled water in/out, condensation collection & drainage.
Title: Re: DYX
Post by: chin on 26 March 2010, 05:28:19
3月25日

正門接待處間好。冷氣鮮風原來入5部機,不是4部。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:29:32
3月25日

接待處。旁邊會是玻璃?地台弧形石板面已鋪好,用木板保護。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:32:26
3月25日

電梯口鐵閘位。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:33:46
3月25日

原來的女厠正在改成男厠。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:35:21
3月25日

通向兩間大會議室的走廊。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:36:27
3月25日

Corner Conference Room
Title: Re: DYX
Post by: chin on 26 March 2010, 05:37:33
3月25日

大會議室。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:39:00
3月25日

傍邊的儲物房。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:41:26
3月25日

辦公大堂中央東西向兩景。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:42:23
3月25日

接待處背面。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:44:00
3月25日

Chaos hidden above the ceiling. How did they made it so neat in Andy Lau's open ceiling office?!  ???
Title: Re: DYX
Post by: chin on 26 March 2010, 05:45:57
3月25日

準備裝門的辦公室。上面的各色冷氣燈盤。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:46:55
3月25日

玻璃牆位。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:47:29
3月25日

Lap's office  :)
Title: Re: DYX
Post by: chin on 26 March 2010, 05:50:03
3月25日

電線插裝好,CAT5未裝插。
下圖是機房。這麼多線,點分?!  :o
Title: Re: DYX
Post by: chin on 26 March 2010, 05:51:19
3月25日

CAT5網絡線和地面線槽。
Title: Re: DYX
Post by: chin on 26 March 2010, 05:52:00
3月25日

The two smaller windowless meeting rooms.
Title: Re: DYX
Post by: chin on 26 March 2010, 05:57:01
3月25日

電表房內。前面的表板是沒有用的。
為甚麼要做多個表板?
下圖左面深色的金屬柱是甚麼?
Title: Re: DYX
Post by: chin on 26 March 2010, 06:01:20
3月25日

全層一間公司用,唔洗爭位,普通電線入槽已經可以。
原來報價是用armored cable,可能是contractor求穩陣,驚線槽無位,armored一定入到?
Title: Re: DYX
Post by: chin on 26 March 2010, 06:05:34
3月25日

各色電信,電視,廣播,門禁,警報等等線槽。
甚麼是SEC?CABD?
PCCW以外點入線?
Title: Re: DYX
Post by: chin on 26 March 2010, 06:06:11
3月25日

What the heck is this?
Title: Re: DYX
Post by: hangchoi on 26 March 2010, 10:48:31
 ;D ;D If you treat me some nice tea / whisky next time, I don't mind go with you for a site visit and answer all your questions above........ ;D ;D
Title: Re: DYX
Post by: chin on 26 March 2010, 11:03:11
;D ;D If you treat me some nice tea / whisky next time, I don't mind go with you for a site visit and answer all your questions above........ ;D ;D

Yes sir.  ;D
Title: Re: DYX
Post by: chin on 20 April 2010, 00:27:21
4月9日

距離目標入伙日還有一星期。

入口大堂。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:28:40
4月9日

距離目標入伙日還有一星期。

兩個會議室。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:30:23
4月9日

距離目標入伙日還有一星期。

辦公室大堂東西兩個方向景。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:31:50
4月9日

距離目標入伙日還有一星期。

工人忙於切家私。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:32:33
4月9日

 :)

Title: Re: DYX
Post by: chin on 20 April 2010, 00:33:52
I was traveling late Mar to 8 Apr, thus no progress pictures for about 2 weeks.

Too bad.
Title: Re: DYX
Post by: chin on 20 April 2010, 00:52:28
4月16日

中午從海南島回來,晚上到第一線新辦公室看看。明天就要搬了,現在還要最後衝刺,大堂還有很多燈還未上好,招牌少了個字。 ::)
Title: Re: DYX
Post by: chin on 20 April 2010, 00:56:13
4月16日

會議室已經可以用。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:57:54
4月16日

明天同事們就要搬來了,啊聰還要駁二百多條CAT5。
Title: Re: DYX
Post by: chin on 20 April 2010, 00:58:57
4月16日

搬運工人忙於搬家私。
Title: Re: DYX
Post by: chin on 20 April 2010, 01:00:22
4月16日

搬成百人的辦公室不簡單!
Title: Re: DYX
Post by: chin on 20 April 2010, 01:03:21
2月25日收樓,6個星期起貨,4月17日搬入。

Not Bad.
Title: Re: DYX
Post by: chin on 20 April 2010, 01:09:21
4月17日

海哥Wallace在他的辦公室。
Title: Re: DYX
Post by: chin on 20 April 2010, 01:10:47
4月17日

星期六下午,很多同事還未整理好自己的位。
Title: Re: DYX
Post by: chin on 20 April 2010, 01:20:27
Start looking for new office around Sep 2009, decided on Crocodile Center around Dec 2009, negotiated contract and took delivery of space in late Feb 2010, moved in by mid Apr 2010.

See press release at http://dyxnet.com/

Next is my own office.  ;D
Title: Re: DYX
Post by: hangchoi on 20 April 2010, 09:39:36
looks cool...... ;)

Title: Re: DYX
Post by: chanchiwai on 20 April 2010, 17:20:09
looking forward to visiting your new office....
Title: Re: DYX
Post by: chin on 31 January 2011, 17:57:52
First Chinese New Year in the new office.
Title: Re: DYX
Post by: chin on 07 February 2011, 17:06:42
Update 7-Feb-2011
Title: Re: DYX
Post by: chin on 09 February 2011, 16:32:32
Update  :)