hangchoi:
It shows some progress of the work......
Yep, most of the air ducts are now pre-fabricated off-site, as the dimensions of the fan coil units are quite standard.
It seems that the screeding is quite thin and the reinforcement bar should not be exposed when you chase the screeding. Maybe the contactor can use the ceiling more for cable routing, or use 20mm dia. conduit only for cable containment on floor.
What is the fitting out period?? How long did they start the work?? Seems they still need 2 months to complete the work at least.....
chin:
Work started on 26 or so.
chin:
3月10日
入口接待處。
chin:
3月10日
大會議室外,內。上好隔音棉。
chin:
3月10日
冷氣風機,風槽差不多全部上好。冷水管只裝了半層,未接上風機。
下面的風機未上罩?